1. Strip-out
The old suite, tiles and boarding come out, so any hidden problems with floors, walls or pipes can be dealt with early.
2. First fix
New pipework and electrics are run, and the joinery goes in: stud walls, boxing-in, shower niches and noggins to support wall-hung toilets and basins.
3. Boarding and plastering
Walls are boarded with the right boards for wet areas, then plastered or prepared for tiling.
4. Tiling and panelling
Floor and wall tiles go on, along with any panelling or slatted features.
5. Second fix
The bath, shower, toilet, basin, taps and lighting are fitted and connected, and the room is sealed and finished.